The Runaway Costs of Government Construction Projects

Published

13 minute read

From the C2C Journal

By Gwyn Morgan

Ottawa’s post-pandemic $300 billion spending orgy was coupled with the pompous claim to “Build Back Better”. As it happened, most of that spending was recklessly borrowed – stoking inflation – while Build Back Better was a dud, was discarded in embarrassment and, if recalled at all today, is told as a sick joke. Far too many planned projects now sink into a quicksand of political haggling, regulatory overkill, mission creep, design complexity and, if built at all, bungled execution. Looking at specific examples, Gwyn Morgan presents the lamentable results: far less is actually getting built across Canada, nearly everything takes forever and – worst of all – costs routinely soar to ludicrous levels. Added to that, Morgan notes, are woke-based criteria being imposed by the Trudeau government that are worsening the vicious cycle.

Not so long ago, a $10 million government infrastructure project was regarded as a significant expenditure. Nowadays, $10 million doesn’t come close to funding projects as simple as a firehall or new police station. Here in the Victoria region, a new firehall in the District of Saanich, originally budgeted at $25.6 million, has jumped to nearly $45 million over four years – and construction has barely begun. The facility will support 10 firefighters. In the Langford District, the estimated cost of a new RCMP building is an incomprehensible $82 million – and of course, nothing has actually been done yet, so this price tag will surely soar. Just north of Victoria, the cost of what was to be a simple flyover eliminating a dangerous left turn across the busy Patricia Bay Highway has spiked from its original estimate of $44 million to $77 million.

These cost increases seem big to us here on “Fantasy Island”, but they would amount to a rounding error in mega-city Toronto. The Ontario Line, a 15.6-kilometre light-rail transit line connecting the Science Centre to Ontario Place, was budgeted at $10.9 billion when first announced in 2019. A series of updates have seen the cost balloon to an estimated $19 billion – an increase of more than 70 percent – with the completion date pushed out by four years to 2031. Expect more cost increases to be announced.

These are just a few examples of municipal and provincial cost increases and overruns. The story is similar from coast to coast, with no project type or size in any municipality or province immune to an unsettling syndrome that seems to prevent nearly anything from being planned cost-effectively and then delivered on budget. Obviously, the total for all such projects planned or underway across Canada is immensely higher – surely in the tens of billions of dollars.

Mismanagement syndrome: From simple firehalls to subway sections to straightforward software, governments at all levels have lost control of costs. Replacing a small firehall in Saanich on Vancouver Island (top left and top right) will cost nearly $2,000 per square foot or $4.5 million per firefighter; the pricetag for Toronto’s planned Ontario Line (bottom left) has zoomed from $10.9 billion to $19 billion; and the notorious ArriveCAN (bottom right) consumed $54 million to deliver an $80,000 software tool. (Sources of images: (top left) District of Saanich; (top right) rendering courtesy of hcma, retrieved from naturally:wood; (bottom left) Metrolinx; (bottom right) WestJet/Facebook)

Now for the project mismanagement champion of all. Statistics Canada data show that federal capital infrastructure project expenditures totalled $24.1 billion in the period 2018-2021 (the most recent year for which figures are available). Given that Ottawa bureaucrats are famous for mismanaging virtually every project (think of the notorious ArriveCAN app, whose development blew through $54 million to yield a buggy software tool that private-sector geeks could have cranked out for $80,000), there can be no doubt that a lot of those billions were to pay for overruns resulting from a combination of sloppy design specifications and poor execution.

But now the Trudeau government has added costly “social justice” specifications to federal procurement requirements, including participation by ethnic minorities, disabled persons and diverse genders, plus other elements of woke ideology. These elements were clearly demonstrated in what I’ll call “The Great Helicopter Hangar Saga”. The following is a recollection from sources I know to be completely reliable.

The Canadian Forces’ 443 (Pacific) Maritime Helicopter Squadron’s hangar had been located adjacent to the Victoria Airport for many years. In November 2004, the Department of National Defence (DND) announced the award of a $1.8 billion contract for 28 Sikorsky CH-148 Cyclone helicopters, of which a number were to be based on Vancouver Island. A new hangar was required, which seems reasonable. DND engineers designed a facility that would meet the squadron’s needs at an estimated cost of roughly $18 million. Then they handed the project to Public Works and Government Services Canada. That’s when the project entered an ephemeral space resembling the old sci-fi TV series The Twilight Zone.

Public Works decided the hangar needed to be able to “sustain operations” in the event of a magnitude 8.0 earthquake – an incomprehensible decision for several reasons. First, 8.0 on the Richter Scale is seven times larger than the most severe earthquake ever recorded on Vancouver Island. Second, the severity of earthquake damage at any given location depends on its subsurface. Buildings sitting on soil and gravel suffer much more damage than those built on bedrock because the soft material changes from behaving like a solid to behaving like a thick liquid, amplifying the ground’s shaking. The Pacific Maritime Helicopter Squadron’s hangar was located on solid bedrock. That alone made it highly earthquake-resilient.

But the Public Works technocrats were oblivious to those facts, or didn’t care. Instead, their design demanded steel piles driven into the bedrock at a cost of $8 million. That alone reportedly delayed the project by two years. Cross-bracing of the interior wall openings added more millions. When construction of the actual building finally began, government bureaucrats specified more office space, locker and “administrative security” facilities than what the DND had considered necessary, adding more costs.

Then came the woke-related costs. In determining the contract award, Public Works required First Nations involvement both as subcontractors and in the workforce, extensive gender diversity and complete disabled access. Elevators were ordered equipped with Braille at the control buttons plus voice recognition – along with full wheelchair accessibility. Members of the military joked that all these extras must be for the “blind and disabled pilots”. By the time the new hangar was handed back to the military, the DND’s $18 million project had skyrocketed to a staggering $155 million.

Braille for blind pilots: To base some of the Royal Canadian Air Force’s new CH-148 Cyclone maritime helicopters (above, performing in-flight refuelling with a navy frigate in the North Atlantic) on Vancouver Island, federal Public Works bureaucrats took a reasonable $18 million Department of Defence design and transformed it into a $155 million fiasco reflecting Ottawa’s diversity obsessions and wokist ideology. (Sources of photos: (top) Lockheed Martin, retrieved from Navy Recognition; (bottom) The Lookout)

In July 2019, Phillip Cross wrote an inciteful column for the Financial Post entitled, “Why governments keep screwing up major infrastructure projects”. As Cross put it, “Prominent studies of domestic and international public infrastructure projects found cost overruns averaged between 45 and 86 percent.” Why? In Cross’s view, a big part of the problem is that “public projects suffer from a lack of accountability. Governments evaluate projects not according to the performance-based criteria of the private sector, but by their conformity to rules and processes.”

Cross’s points are well-taken and illustrated by circling back to our Saanich Firehall example. The new facility’s 23,476 square feet will incur a construction cost of over $1,900 per square foot (assuming the new $45 million budget is big enough). That is six to nine times typical construction costs for commercial buildings which, as this report shows, average $200-$300 per square foot. And while a firehall may well be a bit more sophisticated and hence costly to build than, say, a retail strip mall, the Saanich firehall’s costs are also wildly out of proportion to any class of construction, as the fascinating accompanying chart shows. As you can see, it lists a range of $415-$485 per square foot for emergency services buildings. Even technology-heavy, highly customized construction categories like hospitals and data centres come in at no more than $805 and $1,055 per square foot, respectively. Clearly, something is seriously wrong in Saanich and many other locations across Canada.

Outrageous by any standard: The ballooning construction costs of recent public-sector projects are many times higher than 2022 averages for all categories – even in a high-cost market like Vancouver. (Source of graph: Statista)

This evidence of dysfunctional project mismanagement comes at a time when public infrastructure spending is at record levels, dominated by the Justin Trudeau government’s $33 billion 2023-24 infrastructure project budget and sure to be made even more dysfunctional and costly by the Liberals’ surreptitious implementation of woke ideology. When will Canadians awaken and rise up against a government that defies the values of honesty and openness our country was built on?

Gwyn Morgan is a retired business leader who was a director of five global corporations.

Source of main image showing Vancouver’s Broadway Subway project: BC Ministry of Transportation and Infrastructure; retrieved from ReNew Canada.

2025 Federal Election

As PM Poilievre would cancel summer holidays for MP’s so Ottawa can finally get back to work

Published on

From Conservative Party Communications

In the first 100 days, a new Conservative government will pass 3 laws:

1. Affordability For a Change Act—cutting spending, income tax, sales tax off homes

2. Safety For a Change Act to lock up criminals

3. Bring Home Jobs Act—that repeals C-69, sets up 6 month permit turnarounds for new projects

No summer holiday til they pass!

Conservative Leader Pierre Poilievre announced today that as Prime Minister he will cancel the summer holiday for Ottawa politicians and introduce three pieces of legislation to make life affordable, stop crime, and unleash our economy to bring back powerful paycheques. Because change can’t wait.

A new Conservative government will kickstart the plan to undo the damage of the Lost Liberal Decade and restore the promise of Canada with a comprehensive legislative agenda to reverse the worst Trudeau laws and cut the cost of living, crack down on crime, and unleash the Canadian economy with ‘100 Days of Change.’ Parliament will not rise until all three bills are law and Canadians get the change they voted for.

“After three Liberal terms, Canadians want change now,” said Poilievre. “My plan for ‘100 Days of Change’ will deliver that change. A new Conservative government will immediately get to work, and we will not stop until we have delivered lower costs, safer streets, and bigger paycheques.”

The ’100 Days of Change’ will include three pieces of legislation:

The Affordability–For a Change Act 

Will lower food prices, build more homes, and bring back affordability for Canadians by:

We will also:

  • Identify 15% of federal buildings and lands to sell for housing in Canadian cities.

The Safe Streets–For a Change Act 

Will end the Liberal violent crime wave by:

The Bring Home Jobs–For a Change Act 

This Act will be rocket fuel for our economy. We will unleash Canada’s vast resource wealth, bring back investment, and create powerful paycheques for workers so we can stand on our own feet and stand up to Trump from a position of strength, by:

Poilievre will also:

  • Call President Trump to end the damaging and unjustified tariffs and accelerate negotiations to replace CUSMA with a new deal on trade and security. We need certainty—not chaos, but Conservatives will never compromise on our sovereignty and security. 
  • Get Phase 2 of LNG Canada built to double the project’s natural gas production.
  • Accelerate at least nine other projects currently snarled in Liberal red tape to get workers working and Canada building again.

“After the Lost Liberal Decade of rising costs and crime and a falling economy under America’s thumb, we cannot afford a fourth Liberal term,” said Poilievre. “We need real change, and that is what Conservatives will bring in the first 100 days of a new government. A new Conservative government will get to work on Day 1 and we won’t stop until we have delivered the change we promised, the change Canadians deserve, the change Canadians voted for.”

Continue Reading

Automotive

Canadians’ Interest in Buying an EV Falls for Third Year in a Row

Published on

From Energy Now

Electric vehicle prices fell 7.8 per cent in the last quarter of 2024 year-over-year, according to the AutoTader price index

Fewer Canadians are considering buying an electric vehicle, marking the third year in a row interest has dropped despite lower EV prices, a survey from AutoTrader shows.

Forty-two per cent of survey respondents say they’re considering an EV as their next vehicle, down from 46 per cent last year. In 2022, 68 per cent said they would consider buying an EV.

Meanwhile, 29 per cent of respondents say they would exclusively consider buying an EV — a significant drop from 40 per cent last year.

The report, which surveyed 1,801 people on the AutoTrader website, shows drivers are concerned about reduced government incentives, a lack of infrastructure and long-term costs despite falling prices.

Electric vehicle prices fell 7.8 per cent in the last quarter of 2024 year-over-year, according to the AutoTader price index.

The survey, conducted between Feb. 13 and March 12, shows 68 per cent of non-EV owners say government incentives could influence their decision, while a little over half say incentives increase their confidence in buying an EV.

Continue Reading

Trending

X