Alberta’s Massive Carbon Capture and Storage Network clearing hurdles: Pathways Alliance

From the Canadian Energy Centre
By Will GibsonPipeline front-end engineering and design to be complete by end of year
Canada’s largest oil sands companies continue to advance a major proposed carbon capture and storage (CCS) network in northeast Alberta, including filing regulatory applications, conducting engineering and design, doing environmental surveys and consulting with local communities.
Members of the Pathways Alliance – a group of six companies representing 95 per cent of oil sands production – are also now closer to ordering the steel for their proposed CO2 pipeline.
“We have gone out to potential pipe suppliers and asked them to give us proposals on costs and timing because we do see this as a critical path going forward,” Imperial Oil CEO Brad Corson told analysts on November 1.
He said the next big milestone is for the Pathways companies to reach an agreement with the federal and provincial governments on an economic framework to proceed.
“Once we have the right economic framework in place, then we will be in a position to go order the line pipe that we need for this 400-kilometre pipeline.”
Pathways – which also includes Suncor Energy, Canadian Natural Resources, Cenovus Energy, MEG Energy and ConocoPhillips Canada – is proposing to build the $16.5 billion project to capture emissions from oil sands facilities and transport them to an underground storage hub.
The project was first announced in 2022 but Pathways had not provided recent public updates. The organization had stopped advertising and even briefly shut down its website during the summer in wake of the federal government’s amendments to the Competition Act in June.
Those changes include explicit provisions on the need to produce “adequate and proper testing” to substantiate environmental benefit claims. Critics say the provisions could lead to frivolous lawsuits and could or even scuttle the very projects that Canada is relying on to slash greenhouse gas emissions.
In early December, the Alberta Enterprise Group (AEG) and the Independent Contractors and Businesses Association jointly filed a constitutional challenge against the federal government over the new “greenwashing” rules, which they say unreasonably restrict free speech.
“These regulations pre-emptively ban even truthful, reasonable and defensible discussion unless businesses can meet a government-imposed standard of what is the truth,” said AEG president Catherine Brownlee.
Pathways has since restored its website, and president Kendall Dilling said the organization and its member companies continue working directly with governments and communities along the corridors of the proposed CCS project.
Canadian Natural Resources began filing the regulatory applications to the Alberta Energy Regulator on behalf of Pathways earlier in the year. The company has so far submitted 47 pipeline agreement applications along with conservation and reclamation plans in seeking approvals for the CO2 transportation network.
Pathways has also continued consultation and engagement activities with local communities and Indigenous groups near its pipeline corridors and storage hubs.
“Engagement is ongoing with local communities, Indigenous groups and landowners, as well as a consultation process with Indigenous groups in accordance with Aboriginal Consultation Office requirements,” Dilling says.
An environmental field program that began in 2021 continues to survey the network’s project areas.
“Environmental field studies are ongoing and we are supporting Indigenous groups in completing traditional land use studies,” Dilling says.
“Studies are supported by hundreds of heritage resource assessments, wetland classifications, soil assessments, aquatic habitat evaluations and other environmental activities.”
In addition to working with governments and communities, Pathways expects front-end engineering and design on the proposed 400-kilometre-plus main transportation line and more than 250 kilometres of connecting pipelines to be complete by the end of this year.
Pathways has also drilled two test wells in the proposed storage hub and plans to drill another two or three evaluation wells in the final quarter of 2024.
Alberta
Red Deer Justice Centre Grand Opening: Building access to justice for Albertans

The new Red Deer Justice Centre will help Albertans resolve their legal matters faster.
Albertans deserve to have access to a fair, accessible and transparent justice system. Modernizing Alberta’s courthouse infrastructure will help make sure Alberta’s justice system runs efficiently and meets the needs of the province’s growing population.
Alberta’s government has invested $191 million to build the new Red Deer Justice Centre, increasing the number of courtrooms from eight to 12, allowing more cases to be heard at one time.
“Modern, accessible courthouses and streamlined services not only strengthen our justice
system – they build safer, stronger communities across the province. Investing in the new Red Deer Justice Centre is vital to helping our justice system operate more efficiently, and will give people in Red Deer and across central Alberta better access to justice.”

Government of Alberta and Judiciary representatives with special guests at the Red Deer Justice Centre plaque unveiling event April 22, 2025.
On March 3, all court services in Red Deer began operating out of the new justice centre. The new justice centre has 12 courtrooms fully built and equipped with video-conference equipment to allow witnesses to attend remotely if they cannot travel, and vulnerable witnesses to testify from outside the courtroom.
The new justice centre also has spaces for people taking alternative approaches to the traditional courtroom trial process, with the three new suites for judicial dispute resolution services, a specific suite for other dispute resolution services, such as family mediation and civil mediation, and a new Indigenous courtroom with dedicated venting for smudging purposes.
“We are very excited about this new courthouse for central Alberta. Investing in the places where people seek justice shows respect for the rights of all Albertans. The Red Deer Justice Centre fills a significant infrastructure need for this rapidly growing part of the province. It is also an important symbol of the rule of law, meaning that none of us are above the law, and there is an independent judiciary to decide disputes. This is essential for a healthy functioning democracy.”
“Public safety and access to justice go hand in hand. With this investment in the new Red Deer Justice Centre, Alberta’s government is ensuring that communities are safer, legal matters are resolved more efficiently and all Albertans get the support they need.”
“This state-of-the-art facility will serve the people of Red Deer and surrounding communities for generations. Our team at Infrastructure is incredibly proud of the work done to plan, design and build this project. I want to thank everyone, at all levels, who helped make this project a reality.”
Budget 2025 is meeting the challenge faced by Alberta with continued investments in education and health, lower taxes for families and a focus on the economy.
Quick facts
- The new Red Deer Justice Centre is 312,000 sq ft (29,000 m2). (The old courthouse is 98,780 sq ft (9,177 m2)).
- The approved project funding for the Red Deer Justice Centre is about $191 million.
Alberta
Made in Alberta! Province makes it easier to support local products with Buy Local program

Show your Alberta side. Buy Local. |
When the going gets tough, Albertans stick together. That’s why Alberta’s government is launching a new campaign to benefit hard-working Albertans.
Global uncertainty is threatening the livelihoods of hard-working Alberta farmers, ranchers, processors and their families. The ‘Buy Local’ campaign, recently launched by Alberta’s government, encourages consumers to eat, drink and buy local to show our unified support for the province’s agriculture and food industry.
The government’s ‘Buy Local’ campaign encourages consumers to buy products from Alberta’s hard-working farmers, ranchers and food processors that produce safe, nutritious food for Albertans, Canadians and the world.
“It’s time to let these hard-working Albertans know we have their back. Now, more than ever, we need to shop local and buy made-in-Alberta products. The next time you are grocery shopping or go out for dinner or a drink with your friends or family, support local to demonstrate your Alberta pride. We are pleased tariffs don’t impact the ag industry right now and will keep advocating for our ag industry.”
Alberta’s government supports consumer choice. We are providing tools to help folks easily identify Alberta- and Canadian-made foods and products. Choosing local products keeps Albertans’ hard-earned dollars in our province. Whether it is farm-fresh vegetables, potatoes, honey, craft beer, frozen food or our world-renowned beef, Alberta has an abundance of fresh foods produced right on our doorstep.
Quick facts
- This summer, Albertans can support local at more than 150 farmers’ markets across the province and meet the folks who make, bake and grow our food.
- In March 2023, the Alberta government launched the ‘Made in Alberta’ voluntary food and beverage labelling program to support local agriculture and food sectors.
- Through direct connections with processors, the program has created the momentum to continue expanding consumer awareness about the ‘Made in Alberta’ label to help shoppers quickly identify foods and beverages produced in our province.
- Made in Alberta product catalogue website
Related information
-
Business2 days ago
Chinese firm unveils palm-based biometric ID payments, sparking fresh privacy concerns
-
2025 Federal Election2 days ago
Conservatives promise to ban firing of Canadian federal workers based on COVID jab status
-
Business1 day ago
Is Government Inflation Reporting Accurate?
-
2025 Federal Election1 day ago
Carney’s Hidden Climate Finance Agenda
-
International2 days ago
Pope Francis Got Canadian History Wrong
-
Environment2 days ago
Experiments to dim sunlight will soon be approved by UK government: report
-
Censorship Industrial Complex2 days ago
Is free speech over in the UK? Government censorship reaches frightening new levels
-
2025 Federal Election1 day ago
When it comes to pipelines, Carney’s words flow both ways